Delivery of the required construction materials will start at the end of April 2019. At the same time, a temporary platform will be erected. As the lead consortium partner, PORR is responsible in particular for the construction of the superstructure and substructure, island platforms and a culvert.
The project is expected to be completed in the second half of October 2019, parallel to the commissioning of the new security system.